step 11 back wall: Tokonoma |
![]() |
step 12 back wall completion: flooring and cabinets. |
![]() |
step 13 finished interior floor: interlocking rubber tiles |
![]() |
step 14 box beams assembled from splieced sections. tie down to shear panel supports. anteroom sliding panels and shoe storage shelves. |
![]() |
step 15 wood truss placement. shipped in two and assembled on site |
![]() |
step 16 top tie insertion |
![]() |
step 17 gable closure. lower roof panels: eps hybrid stressed skn panel. upper surface is metal standing roof with interlocking battens. |
![]() |
step 18 upper roof panels: similar to lower panels. recessed gutter. slope to rear. |
![]() |
step 19 clerestroy and exterior sliding panels: laminated polycarbonate in braced frames. |
![]() |
step 20 site imprveoments. entry stones. portable toilets at rear. gutters empty along chains to rain barrels. |



![]() |
step 1 site preparation |
![]() |
step 2 footing and concrete pier placment. gravel path at perimeter |
![]() |
step 3 floor beam assembly. tie down to piers. |
![]() |
step 4 presealed eps stressed skin 8' x 16' floor deck panels with integral joists |
![]() |
step 5 veranda and anteroom weatherproofing. flash edges. |
![]() |
step 6 threshold placement as panel spacer. |
![]() |
step 7 shear panel placement. 4' x 8' hybrid eps stressed skin panels selaed and paint ready. |
![]() |
step 8 panel placement and top strap shear connections. |
![]() |
step 9 complete top strap ties. finished lower enclosure. |
![]() |
step 10 back wall: prefabricated closet. |